First Bridge Installed at our Crossrail West Project

Our Ealing Broadway team has successfully installed the Crossrail West projects first complete bridge.

The installation took place on 21-22 May during a standard 12-hour shift, avoiding the need for a full line possession to complete the works.

Fast Facts:

276 person hours worked over the 12 hour shift
300t crane was used for the lift
10.1t was the heaviest lifting load and the total of steel lifted was 29.7t

The works at Ealing Broadway are part of a project across 14 sites from Acton to Maidenhead on the Great Western line to modify the stations to accommodate the operation of the new 10-car, 205m long Crossrail trains.


 

Back...

Click to download